Kerala - Kochi
Hudco Project: re-tendering process on
Staff Reporter
KOCHI: The re-tendering of the pipe-laying work from Kathrikkadavu to Konthuruthy for the Ad hoc Water Supply Augmentation Scheme (Hudco Project) is now being processed.
The work of laying pipes for the much-awaited Hudco Project should be completed for increasing the pumping capacity to the water-starved areas of West Kochi. The cancellation of the tender earlier given to the FACT Engineering Works (FEW) sparked controversies. The cancelled works included laying of 840 meters of 1,200 mm MS pipeline from Kathrikkadavu to Elamkulam underground sump and 5,105 m of 1,200 mm MS pipeline from Elamkulam to Konthuruthy in West Kochi.
The works were re-tendered in three reaches, instead of the two reaches in the earlier tender. The tenders were opened and being processed. The FEW was reported to have come as the lowest bidder only in one reach. In the other two reaches, it was reported to be the third lowest bidder only.
The public sector unit was almost on the verge of losing the bid.
The Kerala Water Authority Employees' Association, the Congress-led union of the KWA staff, registered its protest against the re-tendering. The KWA management said the work was re-tendered, as the FEW could not complete the work on time. However, the FEW said the delay was caused not because of their fault, but due to the delay in obtaining permission for cutting the roads. The FEW also demanded increased charges from the KWA citing the delay caused the costs to increase.
The laying of pipes for 1,735 m from Samskara Junction to Kathrikkadavu was successfully completed by the FEW.
This work was part of the first phase and the fourth phase of laying 4,280 m of pipeline. Only the laying of 5,955 m of pipelines from Kathrikkadavu to Konthuruthy, a part of the second and third phases of the project, remained to be completed.
Unless the re-tendering process was completed, the hopes of the West Kochi residents for getting the promised water of 25 MLD (million litre per day) when the Hudco project was completed would remain unfulfilled.
(The Hindu - Friday, September 08, 2006)Labels: water